ITER

Consortium INT Government / public Editorial profile Website

Profile

35-nation megaproject building the largest tokamak; first plasma rebaselined to 2034.

Editorial profile — compiled by us from public sources.

Headquarters
Saint-Paul-lès-Durance, France

Current standings

Standings and milestones are always verified by us against primary sources, regardless of who manages the profile.

Roadmap & milestones

ITER — deuterium-tritium operation (planned)

~ 2039
ITER

Full D-T phase under the 2024 baseline; first plasma now 2034.

Central Solenoid complete — world's most powerful pulsed magnet

2026-05
ITER / General Atomics

The 13-tesla, ~1,000-tonne Central Solenoid — the 'beating heart' built by General Atomics to drive ITER's plasma current — is complete and delivered to the site. A key assembly milestone toward first plasma (2034); the full pulsed-magnet system was ~15 years in the making.

First plasma (2024 baseline)

~ 2034
ITER

Start of scientific operation under the rebaselined schedule.

Westinghouse $180M ITER vacuum-vessel contract

2025-06
ITER / Westinghouse

A $180M contract for Westinghouse to complete and weld ITER's vacuum vessel — the hermetic double-walled steel chamber that houses the plasma — joining its nine sectors into a single ring, the most intensive stage of ITER assembly.